Infrastructure upgrade

Scheduled Maintenance Report for MonkDev

Completed

We have rolled back our migration due to performance issues in the new environment.
Posted Jul 20, 2018 - 02:17 PDT

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Jul 20, 2018 - 01:59 PDT

Update

Site API Calls are down while DNS continues to propagate
Posted Jul 20, 2018 - 01:40 PDT

Update

We are in the process of repointing our DNS settings. You may experience momentary loss of content on your website during this update.
Posted Jul 19, 2018 - 23:35 PDT

Update

Our maitenance is still in progess. We will continue to post updates throughout the evening.
Posted Jul 19, 2018 - 20:10 PDT

Update

Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Jul 19, 2018 - 16:59 PDT

In progress

We are starting our planning migration at this time.
Posted Jul 19, 2018 - 16:59 PDT

Scheduled

In an effort to continue providing our customers with best-in-class performance and security we are transitioning data center service providers for our application platform. This transition includes moving and upgrading our web and database servers.

This upgrade will provide enhanced system performance, stability and better security for you and your site visitors.

For more on this, see: https://hello.ekklesia360.com/scheduled-outage-july-2018

Thank you for your understanding during this time.
Posted Jul 03, 2018 - 15:35 PDT
This scheduled maintenance affected: CMS Backend, CMS API, SSL, and Cobblestone.